Phase1 - Complete and In-Service
We’re excited to share that Phase 1 of the Mill Street Substation project is now complete and fully operational. This milestone brings half of the station’s designed energy capacity online.
Phase 2 - In Progress Now
We’ve officially begun Phase 2, the final phase of the Mill Street Substation project. This stage will bring the station to its full design capacity, further enhancing our electrical infrastructure. Here’s what to expect:
- Civil Works and Foundations (In progress until Mid-October): Excavators, dump trucks, concrete trucks, and other heavy machinery will be on site regularly. Please note that this will be the noisiest part of the project.
- Transformer Delivery (Mid-October): On the day of delivery, there will be some parking restrictions along Latimer and Mill Streets. We’ll send out more details to nearby residents as the date approaches.
- Outdoor Equipment Assembly (Mid-October to Mid-November): Crews will be assembling the outdoor equipment needed to bring the substation to full capacity.
- Commissioning (Mid-November to Mid-January): The final commissioning phase will ensure the substation is fully operational and ready to meet the community’s energy needs.
We appreciate your patience and understanding as we work to complete this vital project.