As we head into December, work on the Pier project is continuing with the last few days bringing us blue skies.

Ladybird display building, looking to the north west.

Ladybird display building, looking to the north east.
Inside out view of the Ladybird display building.
Canopy steel construction – anchoring the four corners.
The Canopy structure is a unique shape.
A sunny day on the site, looking south west from the Pier.
This picture offers a perspective of the canopy size.
Swim docks at the Pier are complete.
Work being completed currently:
- North Mountain installed temporary deck protection and prepared site for steel erection.
- MarTech Motor Winding to fabricate and erect canopy steel structure. Steel to be shipped for galvanizing. Steel erection starting tentatively on November 8th.
- Works by City of Nelson, Tru Mechanical and DHC Communications on the Ladybird display. building to install security controls, controls and balance the enclosure systems.
- MarTech Motor Winding erecting canopy steel.
- MarTech Electric installing Ladybird ceiling LED fixtures.
- MarTech Electric hooked up and tested pier handrail lighting.
- North Mountain preparing for canopy wood cladding installation – arranging material orders.
- North Mountain installing steel transition ramps to floating dock gangway ramps.
Contractors on site:
North Mountain Construction, MarTech Electric, MarTech Motor Winding, City of Nelson Staff, DHC Communications and Tru Mechanical